Established in 1971, PCL Industrial Constructors Inc. has grown to become one of Canada’s largest and most diversified heavy industrial contractors. As an industrial general contractor, we are capable of using our own forces to perform a large portion of any industrial project, including process piping, mechanical installations and civil construction. Over the years we have participated in several EPC contracts, in partnership with specialized engineering companies. Through these alliances PCL is able to provide complete design-build construction services.
 |
Plant 25 General Mechanical
Location: |
Fort McMurray, AB |
Description: |
Oil sands vacuum unit and DRU |
Built By: |
PCL Industrial Constructors Inc. |
|
|
|
 |
SCLAIR Major Mechanical
Location: |
Joffre, AB |
Description: |
850-million lb/year polyethylene production facility |
Built By: |
PCL Industrial Constructors Inc. |
|
|
|
 |
Aurora Mine Project
Location: |
Fort McMurray, AB |
Description: |
30,000 BPD oil sands extraction facility |
Built By: |
PCL Industrial Constructors Inc. |
|
|
|
 |
Mainline Compressor Station Construction
Location: |
Windfall, Morinville, & Irma, AB |
Description: |
Mainline compressor stations consisting of 5 - 30,000 hp turbine / compressor sets |
Built By: |
PCL Industrial Constructors Inc. |
|
|
|
 |
Scotford Cogeneration Facility
Location: |
Fort Saskatchewan, AB |
Description: |
80 MW simple cycle power plant |
Built By: |
PCL Industrial Constructors Inc. |
|
|
|
 |
Hydrocarbon Liquids Conservation Project
Location: |
Fort McMurray, AB |
Description: |
170,000 BPD NGL extraction facility |
Built By: |
PCL Industrial Constructors Inc. |
|
|
|
 |
Muskeg River Oil Sands Project
Location: |
Fort McMurray, AB |
Description: |
150,000 BPD oil sands facility |
Built By: |
PCL Industrial Constructors Inc. |
|
|
|
 |
Calgary Energy Centre
Location: |
Calgary, AB |
Description: |
250 MW combined cycle power plant |
Built By: |
PCL Industrial Constructors Inc. |
|
|
|
 |
SWQR - Cogeneration General Mechanical
Location: |
Fort McMurray, AB |
Description: |
80 MW gas turbine, and thermal block on the Aurora site |
Built By: |
PCL Industrial Constructors Inc. |
Delivery Method: |
Traditional Bid [TB] |
|
 |
SWQR - Extraction Structural, Mechanical, Piping, E and I
Location: |
Fort McMurray, AB |
Description: |
General mechanical installations for 10 pumphouses at the Aurora Mine site |
Built By: |
PCL Industrial Constructors Inc. |
Delivery Method: |
Traditional Bid [TB] |
|
 |
CNRL Horizon Priority Works
Location: |
Fort McKay, AB |
Description: |
Deep undergrounds, pre-cast concrete erection, heavy lifts and coke drum steel erection of the temporary construction facilities for the primary upgrader (PUG) site |
Built By: |
PCL Industrial Constructors Inc. |
Delivery Method: |
[TB] Traditional Bid |
|
 |
Minnedosa Ethanol Plant
Location: |
Minnedosa, MB |
Description: |
130 million litre/year grassroots ethanol fuel distillation facility |
Built By: |
PCL Industrial Constructors Inc. |
Delivery Method: |
[TB] Traditional Bid |
|
 |
Syncrude Upgrader Expansion (UE-1) Project
Location: |
Fort McMurray, AB |
Description: |
|
Built By: |
PCL Industrial Constructors Inc. |
Delivery Method: |
Traditional Bid [TB] |
|
|
Contacts
PCL Industrial Constructors Inc.
5402 99th Street NW Edmonton AB T6E 3P4
Phone: (780) 733-5500
industrialinfo@pcl.com
|
 |