This project was engineered and constructed by NEPCO/PCL, A Joint Venture, and consisted of driven steel piles, concrete equipment foundations, a pre-engineered building, installation of a gas turbine generator, heat recovery steam generation, an auxiliary boiler and balance of plant piping, electrical and instrumentation. The project was constructed for Air Liquide Process Construction, Inc. and was built in conjunction with the ALPC Air Separation Facility. PCL Industrial Constructors Inc. performed all of the heavy lift operations on the ASU.
|