Project Description

This project involves the supply and installation of the temporary construction facilities for the Primary Upgrader (PUG) Site, including: office trailers, lunch rooms, wash-cars, warehouse, site preparation of laydown and temporary roads and fencing.

Also included is the following:

  • Supply of a heavy lift crane to install the 4 coker drums, structural steel and Derrick assemblies.
  • Installation of approximately 1400 cast-in-place concrete piles
  • Supply and installation of the sewer system as well as installing the firewater system complete with manholes
  • Installation of the maze basin foundation and complete the site preparation including permanent roads and paving
  • Supply of pre-cast concrete columns

 